Search the Site:


 
Precast Solutions Magazine

Fall 2003

 

Precast Solutions Fall 2003

Park Your Problems Here

Three sites, each with its own unique parking problems, look to precast concrete for answers.

An automobile dealership, a corporate headquarters and a university have little in common, but their directors were thinking alike as they researched a quick and inexpensive way to end their parking woes. Each had its own unique problems, but a precast concrete parking garage was the winning solution in each case. Tindall Corp., a precast concrete manufacturer in Spartanburg, S.C., came to their aid with three entirely different configurations. Each resulted in time and cost savings, and each proved to be aesthetically pleasing additions.

West Side Honda of Knoxville, Tenn., needed more space to store and display its cars, but the dealership was faced with the dual challenges of limited space and a short timeline. Cope Associates, the architects for the project, recommended a high-rise parking structure built with precast concrete components as the ideal solution.

The precaster’s structural design team quickly got to work. Ken Griffin, project engineer with Carpenter Wright Engineers of Knoxville, says, “Tindall Corp. supplied preliminary information on the building load that enabled us to complete the foundation design before the design for the superstructure was done.”

The structure’s design was almost complete when a major budget change was made – forcing Tindall and Cope to considerably trim the project’s size. Alan LaFon, architect with Cope Associates Inc. in Knoxville, explains that the flexibility of precast concrete manufacturing was key, adding, “I can’t imagine how we would have made such a major change in the project if we used cast-on-site construction or a steel structure.”

The local building code authorities were initially hesitant to use precast components, but they were familiar with Tindall’s design team and trusted its engineering specifications. Once the precaster delivered the specifications, the project was quickly approved.

The Rouse Corp. of Knoxville was selected as the general contractor, and the precaster had the shop drawings ready in a few short weeks. The job called for 334 precast concrete components, including columns, beams, spandrels, wall panels, and double tees, all of which were delivered to the job site and ready to install when the contractor needed them – no additional curing time necessary. The 150,000-square-foot project was completed in 25 weeks, although erection of the precast components took only 35 days.

The parking structure melds seamlessly with the rest of the facility, an ideal blend of form and function. West Side Honda has a beautiful space in which to store and display its cars – under budget and on time. The savings in labor hours that resulted from using precast concrete components were a major factor in the cost savings, according to LaFon. He credits a great deal of the project’s success to the early involvement of the precaster.

Early precaster involvement was also the key to success when The Shaw Group, a corporate headquarters in Baton Rouge, La., needed a multilevel parking facility. Shaw wanted a fast-track construction schedule with the flexibility to add floors later if necessary. C.K. Pang of Gensler Architecture says that precast components were well-suited for allowing such speed and flexibility, as well as making accurate timeline planning and cost control much easier.

Tindall Corp. came in early with large-scale mock-ups, allowing Gensler to accurately predict the timeline and cost for this complex project. “Three sides of the site were open, but the fourth side was very crowded,” explains Pang. “Only the teamwork demonstrated by all parties allowed this project to be successful.”

The 598 precast concrete pieces were produced while MAPP Construction Inc., the general contractor, completed the first four levels of the office building. MAPP used the parking deck site as a staging area for materials used in the office building.

The precaster completed the erection of the 225,000-square-foot parking deck well ahead of the office building schedule. Michael A. Polito, president of MAPP Construction, says, “It allowed us to finish the office building without having to worry about finishing the parking deck at the same time.”

Van Nguyen, project architect for Gensler Architecture, added, “The use of precast concrete components in the parking garage helped it to blend in with the office building, which also used a lot of precast concrete.”

Blending in was important to The University of New Orleans. The university needed additional parking space, but school officials did not want the new parking structure to stand out. They also wanted to ensure that the new structure wouldn’t ruin the view of Lake Pontchartrain from two of their other buildings. The project owners, Columbus General Properties LLC, decided on an elongated structure with one elevated level.

“We’ve gotten many compliments on the design, layout and pedestrian feel of this structure,” says Thomas Meric of Duplantier & Meric Architects. The view from a boat on the lake is nice, too – you can just see the cap from the water.” Meric adds that longer spans were possible with precast concrete, allowing them to use fewer columns and providing for a more open interior. That also made campus security happy, because their cameras inside the facility had unobstructed views.

The elevation of the parking structure is nearly the same as that of the nearby office buildings, and the upper-level access ramp is very unobtrusive. These considerations help the garage fit in nicely with the wide-open appearance of the entire campus.

This project used 428 pieces of precast concrete, including 180 double tees, 24 inverted tee beams, 71 columns, 61 spandrels, eight shear walls, 39 stair walls, 29 grade beams and 16 solid flat slabs. It provides more than 100,000 square feet of parking overlooking the lake. The structure was completed in 35 days, largely due to the use of precast concrete components. Major savings in labor hours were also realized by using precast concrete.

“We were interested in a design solution for the parking facility that was attractive and cost efficient,” says Robert Farnsworth, vice president of Columbus General Properties. “We also had to meet an aggressive completion deadline.” He says he knew of some recently completed casinos in Mississippi that used precast parking facilities. “Those facilities had been constructed on aggressive schedules and were generally attractive.”

Farnsworth says he likes precast concrete as a design solution for most parking facilities. “We were able to save time on both the design and construction segments and we ended up with a facility that is both handsome and functional.”

Traditional parking garage construction means building forms, installing rebar, and pouring, testing and finishing the concrete at the job site. It’s far too easy to name the problems that typically come up during these steps – labor problems, material shortages, equipment breakdown, weather. The list seems endless. A predictable timeline for completion can seem like a happy dream when a builder is in the middle of one or more of these issues.

Precast concrete components are made in a factory with strict controls on climate, materials and procedures. After production, component lots are randomly sampled for strength, dimension and consistency to ensure the concrete meets all specifications.

Precast products are manufactured well ahead of time, and therefore delivery can be arranged according to the contractor’s schedule – even for “fast-track” jobs.

Three parking garage projects, three unique sets of problems – all of them solved with precast concrete.

Project Profile
Project Name: West Side Honda
Architect: Cope Associates Inc., Knoxville, Tenn.
Engineer: Carpenter Wright Engineers, Knoxville, Tenn.
Contractor: Rouse Corp., Knoxville, Tenn.
Precast Manufacturer: Tindall Corp., Atlanta, and Tindall Corp., Spartanburg, S.C. *
* Tindall’s Spartanburg plant is certified under NPCA’s Quality Assurance/Plant Certification program.

Project Name: The Shaw Group Corporate Headquarters
Architect: Gensler Architecture, Houston
Contractor: MAPP Construction Inc., Baton Rouge, La.
Precast Manufacturer: Tindall Corp., Biloxi, Miss.

Project Name: University of New Orleans
Architect: Duplantier & Meric Architects, New Orleans
Engineer: Schrenk & Peterson Engineers Inc., New Orleans
Contractor: Broadmoor, New Orleans
Precast Manufacturer: Tindall Corp., Biloxi, Miss.

 
 
The Precast Show