Search the Site:


 
Precast Solutions Magazine

Summer 2003

Precast Solutions Summer 2003

Diversion Tactics

Beneath a busy Phoenix street, a precast concrete stormwater diversion structure saves time and money over the long haul.

Judging a precast concrete vessel by its price tag can be an unfair and inaccurate means of assessing its cost effectiveness. A case in point is a precast stormwater diversion structure installed under a busy Phoenix street last year. While the tender price of the precast vault was higher than that of a cast-in-place concrete vessel, at the end of the day precast proved less expensive.

The massive $75,000 diversion structure, which included two 6-foot by 24-foot precast boxes, was part of a $26 million wastewater treatment plant upgrade. The structure was made of a high-performance concrete by manufacturer Utility Vault, a division of Oldcastle Precast. The company, based in the suburban Phoenix community of Chandler, and project engineer Greeley and Hansen LLC of Phoenix had to overcome a series of unusual challenges to ensure the structure would work.

The idea was to design a diversion stormwater structure for three stormwater pipelines that could support the weight of a heavy sanitary sewer. The problem: The project was being done 30 feet below the middle of the busy Phoenix intersection at 19th Avenue and Durango Street. To minimize traffic disruption, the city stipulated that two of the four lanes had to remain open to traffic and the job had to be completed within 60 days.

After several months of careful planning, the building team set to work and shaved a month off the city’s two-month requirement, says Rich Meyer, project superintendent of Archer-Western Contractors Ltd., contractor for the job. Much of the credit for the speedy finish goes to the precast concrete structures, which were placed in one day. A similar cast-in-place concrete system would have taken three weeks.

The job wasn’t without its complexities. Buried 30 feet below grade, the diversion structure had to carry the weight of the new sewer line and heavy vehicles from a nearby ready-mix plant, a precast plant and some specialty industrial equipment manufacturing facilities. “It is not unusual for us to see six or seven fully loaded (ready-mix trucks) come across this intersection,” notes Jeff Cowee, project manager of Greeley and Hansen LLC. “It had to be a very stout structure and it had to be put in place very quickly. It was a complex job.”

One of the contract stipulations was that the diversion structure had to rely strictly on gravity, not a pump station, to move stormwater, and no standing water was allowed within the structure. To meet the objective, Utility Vault manufactured the two 24-foot-long precast concrete boxes connected by bridges that were large enough to accommodate the water coming through the pipe.

One technical innovation was the engineering and construction of the middle riser ring section of the vault. The large pipe penetrations that cut into the riser required complex three-dimensional finite element analysis to accurately establish all of the forces on each section of the structure, explains Michael Hawes, engineering manager of Utility Vault. With the aid of Finite Element Analysis Software, the precaster’s engineering team developed a cost-effective structure with precise tolerances. Once completed, the correct amount of rebar was specified to distribute the moments correctly and provide adequate shear reinforcement.

But there was another challenge. “The pipeline we were diverting had to be straight, but Murphy’s Law was at work and the line had a little bend. It was enough of a bend to make our work a bit difficult,” says Hawes. What saved the company from working overtime to re-engineer the structure to fit the bend was the flexible modular design, which accommodated the in-field inaccuracies. “Basically we could slide the vault around a bit to fit the bend.”

Before installing the vault, the existing stormwater line had to be cut. Hawes says as a precautionary measure the opening of the line with the least flow was dammed with sandbags and two large water pumps were set up to transport excess stormwater through temporary pipes that ran up and over the excavation site and back down into the downstream end of the stormwater line. The idea was to keep the work site as dry as possible.

In theory the plan was a good one. However, no one expected the sudden surge of water that came through the pipeline which “blew out” the sandbags and filled the work area with 2 to 3 feet of water. “Everyone got wet, but the structure stayed in place,” Hawes notes, adding that the flood would have devastated a cast-in-place concrete vessel under construction. Initially the team expected a day to clean up the mess, but in less than an hour work was back on track.

A 140-ton truck-mounted crane operated by Marco Crane placed each of the massive precast sections, some of which weighed as much as 60,000 pounds, in the 30-foot hole. Meyer, who has never seen a structure that big in the 30 or so years he’s been in the business, says the parking lot of an adjacent truck stop was used as a staging yard. Traffic was held up for 10-minute intervals during the placement of each section over the day-long operation.

The structure is made of 7,000 psi, self-consolidating concrete (SCC). SCC was still a relatively new product in the precast industry when Utility Vault went into production for the job last year, although now many precast manufacturers make products using SCC.

Precast concrete won the day in Phoenix and, in fact, proved that the initial price tag does not equate to final cost. Dollars aside, commuters experienced minimal delays on a busy street, making precast concrete the clear solution for the project.

Project Profile
Project: Stormwater Diversion Structure
Owner: City of Phoenix
Engineers: Greeley and Hansen LLC, Phoenix
Contractor: Archer-Western Contractors Ltd., Chicago
Precast Manufacturer: Utility Vault, a division of Oldcastle Precast Inc., Chandler, Ariz.

 
 
The Precast Show