Lasting Tribute
A national cemetery turns to precast
concrete to ease burgeoning demands for burial
space.
By
Leslie Lichtenburg
An aging veteran population
and an increase in cemetery expansions are compelling
national cemeteries to consider alternative
burial systems. Such is the case at Fort Snelling
National Cemetery in Minneapolis, where a major
expansion program to create space for an additional
21,000 burials is under way.
The growing demand for veteran
burials and the need for a system to accommodate
and expedite burials during the winter months
are driving the trend in pre-placed precast
concrete burial vaults. These enclosed chambers
are installed in quantity, either side-by-side
or multiple depth. The precast units, also known
as lawn crypts, offer a more cost-effective
option for burial with two caskets placed in
one grave with a divider between them. The use
of such pre-placed vaults is becoming popular
in both national and private cemeteries as an
efficient means of expanding cemetery capacity
while at the same time conserving space.
“Using pre-placed crypts
saves space, opens land and enables us to do
more burials for veterans and their dependents,”
explained Don Edmond, assistant director at
the 436-acre Fort Snelling National Cemetery.
Until now, the Fort Snelling
Cemetery relied on a system whereby graves were
pre-dug for winter burials, and tree leaves
- donated by the city - were used as backfill.
“It was easy to dig up the leaves in winter
and install the liners and caskets,” explained
Dave Starkie of the Veterans Affairs (VA) Office
of Facility Management in Washington, D.C.
Today, the use of pre-placed
precast concrete caskets is considered a reliable
solution to the increasing demand for winter
burials. “With pre-placed caskets you
need only a maximum of 18 inches of soil on
top of the crypt, which means that during the
winter, that soil can be easily scraped off,
the lid lifted and the remains interred,”
said Starkie.
The third-largest of the nation’s
120 veterans cemeteries, Fort Snelling averages
18 to 19 burials a day, and sometimes as many
as 25 to 30. With approximately 100 acres still
to be developed and the pace of its burial rate
showing no signs of slowing, the cemetery embarked
on an ambitious expansion program in late spring
of 2003. The project was designed by architects
Sanders Wacker Bergly Inc. of St. Paul, Minn.,
and engineered by Sebesta Blomberg and Associates
of Roseville, Minn. “It was a very unique
project, and somewhat of a challenge in that
we were dealing with a vast area in which to
place these vaults,” said Bill Sanders
of Sanders Wacker Bergly. “Still, there
would be many applications for this type of
burial system. Because it is so efficient, in
terms of land use, it is possible to adapt the
use of pre-placed vaults to many different types
of situations,” he added.
The precast burial vault forms
were engineered and fabricated by Wieser Concrete
Products of Maiden Rock, Wis., which has been
making precast concrete products for nearly
40 years. Frontier Construction of Deer River,
Minn., served as general contractor. “Although
we had a lot of experience with precast concrete
structures, we had never done a project like
this before,” said Jeff Tilden, project
manager for Frontier. “It was challenging,
but with good communication and the right people
on the job, we were able to meet the project’s
very tight timeline.”
Land preparation and excavation
involved three sections of the cemetery comprising
approximately seven acres. More than 100,000
yards of material were excavated and relocated
to accommodate the crypts - averaging 10 to
12 feet deep - and the final grading. Following
excavation, a drain field, piping and a collection
system were put in place, and 8 inches of gravel
bed was laid for a foundation on which to place
the crypts. The crypts, placed 1 inch apart
on the sides and 6 inches apart at the head,
were set and backfilled with pea gravel and
then numbered. Cover material consisted of a
blend of 3 inches of sand and 1 inch of common
material, topped with 4 inches of black dirt.
“Maintaining
spacing was the hardest part of the job because
it was critical to the alignment of the headstones,”
said Tilden. “Sustaining the elevation
was also a challenge.”
Approximately 10,500 single-cavity
burial vaults were required for the project,
a tall order given the project’s budgetary
constraints and short time frame. “In
terms of labor, we needed to be very efficient
in order to produce these vaults,” explained
Andy Wieser, president of Wieser Concrete Products
Inc., the precast manufacturer for the project.
To meet the goals of the project, Wieser Engineering
and Manufacturing Inc., the form manufacturing
division of Wieser Concrete, developed a twin-cavity
burial vault system, which enabled the crew
to produce two castings, or 156 vaults, a day.
All of the vaults were double-depth and some
were double-width, which also sped up construction.
Production of the vaults began in late July,
delivery to the job site commenced one month
later and the contract was completed by Nov.
6.
In addition to expediting
production, Wieser’s unique forming system
created a stronger, more durable product. “These
molds have a thin wall with very little relief,”
explained Wieser. “It’s tough to
strip them without causing cracks or other damage.”
To overcome these challenges, Wieser employed
a pneumatic engineering system that is also
more labor efficient. Actual installation of
the vaults was also streamlined since loading
and handling of vault pieces were minimized
and leveling and setting times were faster.
With installation of the vaults
now complete, the Fort Snelling National Cemetery
expansion is on hold until final grading, roadways
and installation of an irrigation system is
complete. The $6 million project, when completed,
will encompass 22 acres of land, portions of
which will also be developed for standard burial
sites. The pre-placed burial crypts comprise
about one-third of the total project area.
Precast concrete pre-placed
burial vaults are a cost-effective, efficient
method for cemetery expansions that also reduce
the amount of on-site excavation. VA’s
approval of the twin-cavity design system signifies
the need for both public and private cemeteries
to adapt existing land to meet the growing need
for burial space.
To find a manufacturer
of this product in your area or for more information,
visit NPCA’s Web site at www.precast.org
or call toll free (800) 366-7731.
Project Profile
Project
Name: Fort Snelling
National Cemetery, Minneapolis
Owner:
Department of Veterans Affairs
Contractor:
Frontier Construction, Deer River, Minn.
Architect:
Sanders Wacker Bergly Inc., St. Paul, Minn.
Engineer:
Sebesta Blomberg & Associates, Roseville,
Minn.
Precast
Manufacturer: Wieser
Concrete Products Inc., Maiden Rock, Wis.*
* Wieser
Concrete Products Inc. is a certified plant
under NPCA’s Quality Assurance/Plant Certification
program.