Bracing for the Worst
Reinforcing the West Mission Bay
Drive Bridge with precast concrete helps span
the budget gap.
By
Fernando Pagés Ruiz
As you crest the Mission Bay
Drive Bridge heading south into Dana Point,
San Diego, you can’t help but feel a rush
of excitement. This busily traveled precast
concrete girder bridge conveys thousands of
tourists daily to one of the world’s largest
aquatic playgrounds. Captivated by sailboats
cutting blue water and ringed by lavish resorts
and endless palm-lined beaches, you might miss
the 208 precast concrete skirts that help stiffen
the 16 columns supporting your drive over the
channel. Good thing, because the last thing
you want to notice while crossing a bridge is
its substructure - especially in earthquake-prone
California.
Following catastrophic bridge
collapses during the Loma Prieta and Northridge
earthquakes of 1989 and 1994, California engineers
began the laborious and costly process of retrofitting
seismic reinforcement to all of the state’s
overpasses. But along the Mission Bay Drive
Bridge, retrofitting became a little less laborious
and costly by including precast components.
“Without using precast
concrete components, we could not have coped
successfully with the tides or the timeline,”
explains Bill Kotchi, senior civil engineer
for bridges with the City of San Diego Engineering
and Capital Projects Department. Forming and
pouring cast-in-place concrete during the few
hours of low tide and then trying to cure and
complete the project under surging salt water
made precast concrete the natural choice, but
the conditions still presented considerable
challenges.
Difficult
but doable
Imagine the Mission Bay Bridge as a 1,200-foot-long
span arching across an ocean channel between
two peninsulas. As originally built, its substructure
consisted of eight piers or bents and two end
abutments. Each bent had two columns sitting
on its own pile and two separate pile caps with
ocean surging between them.
Engineers wanted to stiffen
this structure by adding additional piles and
tying the separate footings into one big cap.
“We hammered steel piles about 100 feet
deep to reach bedrock on both sides of each
bent and then built a large pile-cap over the
old and new footings to tie the whole thing
together,” explains Kotchi.
The key to tying the separate
footings into one structure involved building
a boat-shaped concrete skirt around each pair
of pile-caps and then filling the resulting
hollow with reinforced concrete. Since the boat-shaped
skirt had to protect the new, monolithic footing
from surging seawater and debris, the contractor
- Traylor Pacific, a division of Traylor Brothers
in Evansville, Ind. - had to erect the structure
at tide level with at least 3 feet of it underwater.
“We considered several
alternatives including the option of building
the entire structure on floating barges and
sinking it into place,” explains Calvin
Casey, project manager with Traylor Pacific.
“But ultimate considerations of cost,
scheduling and risk management made precast
more appealing.” What Casey didn’t
know at bid time was that precast would actually
help complete the project ahead of schedule
and under budget.
Pace
improves after precast components arrive
Compounding the challenge of working in saltwater
surges, Traylor Pacific had to consider the
mating habits of a local seabird. Although it’s
difficult to believe, Mission Bay used to be
a smelly, sandy bog repulsive to humans but
a virtual paradise for the California least
tern. These pigeon-sized, black-and-white birds
have suffered California’s coastal development
enough to join the unfortunate club of endangered
species. Since the rare tern still roosts along
Mission Bay from April to September, Traylor’s
contract included an accelerated completion
schedule - work had to stop before April 1 -
to avoid disturbing the lovebirds’ reproductive
cycle.
The project encountered several
delays at the outset, and even some cost overruns.
Building cast-in-place pile caps suspended over
tidal waters proved more difficult and time-consuming
than predicted. But while Traylor Pacific struggled
with the inherent unpredictability of offshore
construction, San Diego Precast Concrete Inc.
was busy manufacturing the skirts that would
provide form and finish for the bridge’s
6-foot-thick concrete footings.
In a controlled factory environment,
San Diego Precast built 208 precision-cast panels
to within 1/8-inch tolerances encasing epoxy-coated
reinforcement steel bars in a silica fume mix
concrete that would provide resistance to the
corrosive effects of seawater. Since quality
control remained paramount in a structure that
would protect the bridge footings from ocean
scouring, the City of San Diego had laboratory
technicians testing every batch of concrete.
“Every cylinder break exceeded specifications,”
says Kotchi. Curing was also of prime importance.
“But with three days of steam curing at
the precast plant, instead of 14 days on site,
the city was assured a uniform product with
an excellent finish and consistent quality,”
says Kotchi.
San Diego Precast delivered
the 10-inch-thick, 13-foot-tall, 7-foot-wide
panels on schedule. Traylor Pacific closed a
traffic lane on the bridge, plucked each panel
off the deck with a 100-ton hydraulic crane
and lowered it to storage on material barges.
To avoid the difficult coordination
of aligning mechanical fasteners, Traylor Pacific
cast steel angles into the site-built concrete
soffit and had San Diego Precast add steel plates
into the precast panels. As workers lowered
each panel into place, welders stood ready to
fuse the steel connectors.
“We were placing four
panels per hour, exceeding any cast-in-place
method by magnitudes,” says Casey.
The City of San Diego liked
the smooth and uniform finish provided by precast,
which exceeded the tolerances allowable with
a cast-in-place product. After the joints between
each panel were made watertight with a hydraulic
caulk, workers constructed the steel reinforcement
and poured the 6-foot-thick footings that will
help assure the Mission Bay Drive Bridge won’t
collapse even in a major earthquake. Precast
concrete played an important part in bringing
the project in on time and within budget, and
the California least terns enjoyed another peaceful
nesting season.
To
find a manufacturer of this product in your
area or for more information, visit NPCA’s
Web site at www.precast.org
or call toll free (800) 366-7731.
Project Profile
Project:
West Mission Bay
Drive Bridge Seismic Retrofit
Owner:
City of San Diego
Engineer:
TY Lin International McDaniel
Contractor:
Traylor Pacific,
a division of Traylor Brothers, Evansville,
Ind.
Precast
Manufacturer:
San Diego Precast Concrete Inc., Santee, Calif.*
* San
Diego Precast Concrete Inc. is a certified plant
under NPCA's Quality Assurance/Plant Certification
program.