Precast Goes to Extremes
Giant precast endwalls support
a road above a stream in a small Maryland town.
By
Joy LePree
Officials in Taneytown, Md.,
went to extremes in the summer of 2002 during
the construction of a road that connected two
housing developments. Since the road - dubbed
the Crossing at Baumgardner Street - had to
pass over a sizeable stream, engineers knew
tremendous endwalls would be required to support
the avenue and the three 72-inch culvert pipes
needed for the project. Weighing in at 80,000
pounds apiece and measuring more than 28 feet
long and more than 10 feet high, the large precast
endwalls used in the Roberts Mill Run housing
development project are thought to be the biggest
of their kind in the state of Maryland.
Thinking big
While the town may be
small, it is growing rapidly thanks to the addition
of new housing developments. However, in the
case of the Roberts Mill Run housing project,
there was a problem. “In order for traffic
to get from the new subdivision into the existing
one and out onto the main road, a new road had
to be built - but it had to go over a large
stream,” says Gary Hardman, city manager
for Taneytown. “Crossing that stream was
absolutely essential if we were going to connect
the two developments.”
In order to do that, the stream
had to be temporarily diverted so that the two
giant endwalls could be installed and three
72-inch culvert pipes could be pushed through
pre-engineered holes in the endwalls. The endwalls,
which had to be identical, were to be 101/2
feet high and 281/2 feet long and would be placed
directly opposite each other to stabilize the
new road that would be built above them.
The real trick to this sizeable
project was doing it in a timely fashion. “They
needed the roads built quickly so that traffic
could pass over them almost immediately, and
adding to the criticality was the fact that
you don’t want to divert a stream for
too long,” says Hardman.
The contractor saw this as
his biggest challenge. “Working with three
72-inch pipes was tricky enough because they
were the biggest we’ve ever handled, but
disturbing the stream was the real challenge
because it’s something we didn’t
want to do for any longer than absolutely necessary,”
says John Wiley, superintendent of utilities
with project contractors Gray & Son in Butler,
Md. “The longer you disturb a stream,
the greater the chance for disaster.”
Selecting precast
For this reason, Wiley
and his team specified that the endwalls be
made of precast concrete. “Not only does
precast save money when compared to cast-in-place,
but it’s also a huge time savings,”
he says. “Because we used precast for
this project, we only had to divert the stream
for four days. Using cast-in-place would have
taken at least two weeks, and that’s too
long when it comes to diverting a stream.”
Wiley explains that over a two-week period,
a storm could have caused the diverted stream
to flood or the weather could have turned nasty
while the forms were in place waiting for the
concrete to cure.
“There was no question
in my mind that precast had to be the chosen
material for this application,” Wiley
continues. “It was just a matter of finding
someone who could cast such large endwalls in
one piece, because the town engineer insisted
that each one must be cast as one giant endwall
instead of making two smaller pieces for each.”
Casting the big ones
Specifying precast for
the endwalls was the easy part of this project,
but actually casting them was the hard part,
according to Greg Ouimette, president of Frederick
Precast Concrete in Frederick, Md.
“The process of casting
these huge endwalls was pretty intense,”
recalls Ouimette. “We made the hole formers
for the pipes in our fab shop and put them together
with the forms in our shop. Then we had to perform
several inspections before we could even begin
to pour. It was one of the most detailed processes
I’ve ever seen,” he says.
And pouring had to be done
very carefully using a total of four buckets.
“One bucket had to go on the end of each
endwall, and pouring had to occur simultaneously
so the concrete wouldn’t set up on one
end before the other end was finished,”
explains Ouimette. “It took us about four
hours to pour, and during that time we were
monitoring the quality of the concrete to make
sure it wasn’t setting too quickly.”
The precaster stripped the
forms the following day, and the endwalls were
allowed to cure for another two weeks before
they would be touched again. “We wanted
to be sure they would reach full strength,”
says Ouimette. “The mix was a 4,500-psi
mix at 28 days, but we reached 5,800 psi in
two weeks. So we were confident when the contractor
was ready for us.”
An event to be seen
The giant endwalls were
loaded onto lowboy trailers because they were
too tall to be shipped on a regular trailer.
The pieces were carefully removed from the trailers
using pre-engineered lift points and installed
on the site in less than one hour.
“This was remarkable
to watch,” says Hardman. “These
things were each about the size of a bus, and
they were off the truck and in place so quickly
I couldn’t believe it.”
Even Ouimette and Wiley were
impressed with the job. “These guys set
160,000 pounds of solid concrete in less than
60 minutes,” says Ouimette. “It
was truly amazing.”
“I believe these are
the biggest endwalls in the state of Maryland,
so it was really pretty cool that we were able
to make and install them without any problems,”
says Wiley.
Once the endwalls were in
place, the three culvert pipes were pushed through
the pre-engineered holes, cut to size, grouted
and tamped in place. Baumgardener Street was
built in less than a week following this process.
“Precast really worked
out great for this project,” says Hardman.
“It’s really a pretty nice setup
there, and we were really pleased that it was
able to be done so quickly and with such great
results.”
To find a manufacturer
of this product in your area or for more information,
visit NPCA’s Web site at www.precast.org
or call toll free (800) 366-7731.
Project Profile
Project Name:
Roberts Mill Run
Owner:
City of Taneytown,
Md.
Contractor:
Gray & Son, Butler, Md.
Precast
Manufacturer/Engineer: Frederick
Precast Concrete Inc., Frederick, Md.