Precast Takes Center Stage
Precast concrete becomes a part
of history with the construction of the National
Constitution Center’s 350-seat, star-shaped
theater.
By Bridget McCrea
Every year roughly 1 million
visitors will stream into the Kimmel Theater
in Philadelphia to “experience”
a multimedia presentation on the National Constitution
Center’s (NCC) orientation. At some point
during their visit, each one of them will plop
down into a seat in the theater-in-the-round
that features a 360-degree screen around the
perimeter, five smaller screens and a live actor
who presents “The Founding Story.”
The lights dim and the show
begins. An actor in contemporary dress walks
into the middle of the theater and asks: “What
makes us Americans?” As the story progresses,
the media elements change. Filmed elements are
first projected on the floor, next on the 360-degree
screen, then on a scrim that fills the center
of the space, and at key points on the audience
itself. The show ends, as it began, with a question:
“What will we do with freedom?”
Visitors then shuffle out
to the next NCC experience, blissfully unaware
of just how much work went into creating the
350-seat, star-shaped theater where they just
watched the enlightening multimedia production.
Using structural design and construction drawings
provided by Cowan Associates Inc. of Quakertown,
Pa., the precast concrete seating sections for
the circular theater were constructed and erected
by Bethlehem Precast Inc. of Bethlehem, Pa.
Cast in custom-made steel
forms, the curved L-shaped precast concrete
sections for the theater provide the support
structure for five sections of five levels of
seating. According to Charles R. Tomko, Cowan’s
director of structural engineering, the L shape
created the riser and tread sections for the
step theater, and the base sections were recessed
for retractable aluminum stairs. Each section
was welded to steel bearings on sloping steel
girders at the tread and riser via embedded
weld plates.
“Because the steel girders
radiate outward from the middle, the precast
sections had to span increasing widths as they
progressed up the theater and outward in increasing
radii,” Tomko explains. “The precast
is exposed and acts as a walking surface and
support for the theater seats.”
Rich history
The National Constitution
Center (NCC), an independent, nonpartisan, nonprofit
organization dedicated to increasing awareness
about the Constitution and its relevance to
Americans’ daily lives, was created by
the Constitution Heritage Act in 1988. On Sept.
17, 2000, 213 years to the day the U.S. Constitution
was signed, the NCC broke ground with President
Bill Clinton presiding over the official ceremonies.
On July 4, 2003, the two-story NCC opened its
doors.
Located on the third block
of Independence Mall, the NCC joins two of the
nation’s greatest symbols of freedom:
Independence Hall and the Liberty Bell. The
NCC tells the story of the U.S. Constitution
through more than 100 interactive and multimedia
exhibits, photographs, sculptures, texts, films
and artifacts.
The NCC is the first museum
in the country designated as a member of the
National Archives Experience Alliance Initiative.
Precast please
Getting the idea for
the NCC off the drawing board and into reality
required a whopping 85,000 square feet of Indiana
limestone, 2.6 million pounds of steel and a
half-million cubic feet of concrete. Designed
by New York architectural firms Pei Cobb Freed
& Partners and Ralph Appelbaum Associates,
the NCC’s total square footage of public
space is 160,000 square feet, including galleries.
The precast portion of the
NCC consisted of 30 elements comprising 56 yards
of 5,000-psi concrete. Tomko insisted on a high-quality
finish and tight tolerances for the public forum,
and Bethlehem Precast delivered.
Thomas Engelman, president
at Bethlehem Precast, says his firm was invited
to bid on the precast portion of the NCC by
Philadelphia-based Turner Construction, the
project’s general contractor. Engelman
says the idea of creating curved elements for
the amphitheater was unusual for his company,
which decided to take on the challenge and get
involved with the historic project. Originally,
the amphitheater was specified for cast-in-place
concrete, but time constraints and the need
for a more aesthetic, quality look prompted
project owners and engineers to opt for precast
instead.
Chris Auer, project manager
for Turner Construction, says his firm was brought
in to conduct value engineering and cost cutting
for the overall project, which was originally
put out for bid in the fall of 2000. Because
all three bids were over the owner’s budget,
Turner Construction spent a year bringing the
project back in line with the owner’s
projections. “An agreement was reached
in April 2001,” says Auer. “Our
firm gave a guaranteed price to the owner at
that point, and we proceeded with the work.”
Auer says one way his firm
was able to cut costs in the Kimmel Theater
was by switching from cast-in-place to precast
concrete – a move that saved the NCC $87,000
while also shaving several weeks off the construction
time. He says the choice of precast also allowed
the components to be designed by the precast
concrete manufacturer, rather than working from
performance specifications.
One of the most interesting
aspects of the project was the precast pieces
themselves. Not the typical straight sections
of concrete, these 30 elements were cast in
a true radius to form a circular seating area
on which manufactured seating could be arranged.
Engelman says the curved aspect
of the precast structures presented a design
challenge, mainly because each had a different
circumference and radius. “We had to match
the five different levels and all curves within
a half-inch tolerance,” says Engelman,
whose firm has traditionally worked in the residential
sector but recently branched out into more commercial
and industrial applications. “It definitely
made for a tricky job.”
Engelman adds that the precast
portion of the theater not only met but also
exceeded the project owner’s expectations.
It was a feather in the cap of the precaster,
who had never worked with the NCC, nor had it
ever undertaken such an unusual project. “When
they came here to our plant to inspect the pieces
in the middle of the project,” says Engelman,
“they told us that they were much nicer
than they had anticipated.”
Getting the job done
Early on, Auer says several
project participants were reluctant to take
on the task of installing a precast structure
because of its size and weight. To overcome
the objections, he says the contractors modified
original plans and used a tower crane outside
the building to drop the heavy pieces into the
structure. “In one seating area we installed
more joints than were shown on the original
plans, because the structure would have been
too heavy and long,” says Auer.
Engelman says the project
itself took more time than usual to plan out,
which involved such fundamentals as deciding
whether to use wooden or steel forms. “We
make a lot of our forms out of wood, but in
this case it just didn’t pay to do so
because the pieces were so big,” says
Engelman, who subcontracted Spillman Co. to
create the forms for the curved face, side and
back surfaces out of steel. Bethlehem Precast
then manufactured the wooden cores, which aren’t
visible and therefore did not require the same
strict tolerances as the other portions of the
theater.
Because the precast would
be an exposed element within the amphitheater,
the NCC wanted a smooth, quality finish. Unlike
cast-in-place concrete, Engelman says precast
fit the bill perfectly. “I don’t
think they could have ended up with a good,
quality finish from poured-in-place, at least
not without a lot of patching and extra finishing,”
he says. “We used a steel-form finish,
which turned out very smooth and of very high
quality.”
Engelman and Auer both agree
that using precast concrete created time efficiencies
for the project. “We gave them a quick
way to get their amphitheater started,”
says Engelman. “We started in November,
the steel forms arrived in December and by the
end of January all of the pieces were made and
ready to install.”
The expedient work continued
at the job site, where Bethlehem Precast hired
an erector to install the pieces and weld them
into place within two days. The same task would
have taken a construction crew using cast-in-place
concrete two days to complete just one of the
five levels, says Engelman. “The crane
was able to set the steel while the pieces were
being aligned and set manually,” he explains.
“We were in and out in two days, and saved
the NCC a few weeks by getting it up and installed
quickly instead of spending days craning, bucketing
and moving (wet) concrete.”
Impressive results
Auer vividly remembers
the day the NCC executives clambered into what
would soon become the Kimmel Theater to touch,
feel and see the structure’s precast concrete
seating section. “It was one of the first
finished products in the building,” Auer
says, “so everyone was walking around
and sitting on the precast, envisioning what
the theater was going to be like.”
Emily Bittenbender, the NCC’s
vice president of design and construction, also
remembers that day and the milestone that it
represented on what would wind up being a three-year-long
project. Bittenbender, who has since left the
NCC to open her own firm, says she worked closely
with project management group Hill International
to coordinate everything from the architects
and exhibit designers to the sculptors and fabricators,
brining the NCC to life.
The decision to use precast
came after the original bids came in over budget,
Bittenbender says. “Using precast not
only saved us $87,000,” she says, “but
it also made for a pretty straightforward, easy
installation. It was a great solution for our
budget problem and time constraints.”
Overall, Bittenbender
says the NCC was “extremely pleased”
with the end result and the fact that the precast
presented no design or installation challenges
that couldn’t be resolved quickly. “Switching
from cast-in-place to precast was really no
sweat at all,” she says. “It has
provided a great foundation for what is the
center core of the entire building and one of
its most important rooms and functions.”
Project Profile
Project: A
350-seat, star-shaped amphitheater within The
National Constitution Center.
Owner:
The National Constitution
Center, Philadelphia
Architect/Engineer: Pei Cobb Freed & Partners,
New York; Ralph Appelbaum Associates, New York;
Cowan & Associates Inc., Quakertown, Pa.
Contractor/Installer:
Turner Construction Inc., Philadelphia
Precast Manufacturer:
Bethlehem Precast
Inc., Bethlehem, Pa.
Back
to top