All About the Deadline
Precast concrete delivers a much-needed
water tank – fast
By
Daina Manning
Building a water tank is one thing.
Finishing all the precast concrete production in eight
days is quite another. But that was the challenge
Dutchland Inc. faced with the Reserves at Eagle project
in Chester Springs, Pa.
"We bid the job, they imposed [a quick deadline]
on us mid-stream and we just geared up," recalls
David Beiler, sales engineer for Dutchland Inc., Gap,
Pa. "We realized the client we were serving here
was one of the largest -residential builders in the
United States, and in order to meet the demands of
a very large and good client, we just ratcheted up
and got the job done."
The proposed structure was essentially a water recycling
center associated with an upscale housing development:
the station and tank receive clean-treated wastewater,
which is then dispersed into open land through drip
fields for irrigation.
"The homes were selling fast," says Beiler.
"This facility needed to be in operation for
them to continue to sell homes – [buyers] couldn’t
get occupancy permits to move into their homes until
this project was done."
The project was originally specified for cast-in-place
concrete, says Matt Boggs, project manager for Yerkes
Associates, Westchester, Pa. Additionally, the original
designs had the cast-in-place tank outside the building,
says Sandra L. Morgan, P.E., assistant project manager
for URS Corp., Wilmington, Del.
But this approach posed several problems. "[The
developers] waited to start construction until fairly
late, and under weather conditions that would not
be the most advantageous for cast-in-place concrete,"
says Morgan.
"There’s no way they could have [made that
deadline with] cast-in-place," says Beiler. "You’re
fighting the weather, temperatures and all the challenges
associated with outside, on-site construction."
Water tank construction efforts are eased when the
panels that comprise it can be poured horizontally
– a process somewhat analogous to painting a
door when it’s hung as opposed to a door lying
flat on the ground.
For precast concrete, the sections that comprise the
tank can be poured in steel forms laying flat on the
floor, so that it has great width and length but the
height equals the thickness of the finished piece.
For cast-in-place, it’s necessary to pour a
section that has great height and length but a narrow
width. It becomes a much more challenging and hazardous
project to assemble, requiring scaffolding, bracing
and a longer time frame.
When the Reserves at Eagle project needed a faster,
easier way to accomplish the job, "the contractor
came up with the idea for going precast to speed things
up," says Boggs.
Dutchland geared up for the construction equivalent
of finishing a term paper by pulling an all-nighter,
which was made possible with the controlled environment
of a precast plant. "If you’re doing it
on site, you can [only] form up so much in a day,
and you can only cast so much in a day," says
Beiler. "But when you’re in a large precast
production facility, you’re able to do multiple
pours in a day’s time. That’s what allows
us to shorten the time frame."
Then "it was a matter of basically allocating
additional manufacturing resources toward it, more
floor space pouring more panels per day," says
Beiler. A higher-strength concrete formulation was
also used to attain faster curing. “We could
ship the panels to the site in a time frame that was
less than normal," he says. Each section of the
tank was a custom piece, although stock forms could
be utilized by adjusting for thickness and width.
Once complete, the sections were transported to the
site. "We have large hydraulic cranes that are
able to sit next to the excavation, pick the sections
right off the truck and right into the final resting
place," Beiler says.
For the final phase of the project, the precaster
applied post-tensioning technology. "The foundation
of the tank is cast on the site, flat, and then the
precast sections are put into place," Beiler
says. "Then they’re all pulled together
and compressed by cables that we insert into the wall,
pull it all together and lock and seal it off.”
Beiler
explains that in post-tensioning, high-strength steel
compresses the structure’s joints and makes
them watertight. “You’ve got a structure
with a lot of energy pulling it together."
Precasting also led to a major design change for the
project: Instead of a separate unit, the tank was
now located beneath the building. Following the subterranean
excavation, the top of the precast tank – at
ground level – served as the foundation of the
building. Precast proved advantageous for this space-saving
configuration, which was not possible with alternatives
such as a cast-in-place or steel tank or an open pond.
The latter entails the safety risks of people falling
into the pond, and it also becomes a mosquito attraction,"
Beiler says.
Despite less than ideal circumstances, the project
came together smoothly. Boggs says that using precast
concrete makes life easier for engineers due to quality
control standards. "When you use cast-in-place,
you need to supply the structural calculation,”
he says. “[As for] precast, the liability is
on the [precaster] to come up with the correct sizing
and certifications for the structure."
For this project, the precaster was also subject to
detailed inspection. "The township had an inspector
there," Boggs says. Morgan points out that the
wastewater facilities were constructed by the developers,
but will be dedicated to the township. "So the
township is actively reviewing the design and construction
to make sure it conforms to township standards."
Apparently, everyone liked what they saw: Boggs recounts
that the precasters later received an amiable letter
stating how well things went and how quickly the project
was put into place. “It was very complimentary."
Precast concrete proved itself as the go-to material
of choice when the job was both challenging and deadline
driven.
Project Profile
Project: Reserves at Eagle,
Chester Springs, Pa.
Owner: Toll Bros./Upper
Uwchlan Township, Chester County, Pa.
Engineers: Yerkes Associates,
West Chester, Pa.
Contractor: MGK Industries
Inc., Pottstown, Pa.
Precast Manufacturer:
Dutchland Inc., Gap, Pa.
* Dutchland Inc. is a certified plant under NPCA’s
Quality Assurance/Plant Certification Program.