MagLev at Mach 10
Speed, precision and a 'Yes, we can'
attitude evolves into a sound barrier-busting project.
By Greg Snapper
In
the New Mexico desert 100 miles north of El Paso,
Texas, wedged between the San Andreas and Sacramento
mountains, a high-speed military test track grows
longer and time trials get faster with every precast
concrete section that’s installed.
So far, 120 precast sections have been transported
to Holloman Air Force Base in New Mexico to provide
guideway beams for a magnetically levitated test track.
The project is commonly known as the MagLev Upgrade,
and the U.S. Air Force’s 46th Test Group is
building this military track for weapons systems testing
that uses a rocket-mounted sled designed to reach
Mach 10. The Air Force foresees the project as a five-mile
test track running alongside its existing 10-mile
test track, which currently holds the world record
as the longest (almost 10 miles) and fastest (6,453
mph) test track. Both tracks run parallel and serve
the same basic purpose, but the MagLev’s track
will provide a more realistic, low-vibration environment.
David Minto, technical director for the Holloman High
Speed Test Track, said the track is bound to raise
some eyebrows. “I’m sure for Precast Solutions,
this is going to be unusual.” Minto is right.
What’s more impressive is that it’s a
first for the precast concrete industry.
A need for
Mach speed
In
early 2004, San Diego-based high-technology systems
developer, General Atomics, approached precast manufacturer
San Diego Precast Concrete Inc. to cast 150 specialized
precast rail units for the Air Force. But before the
project mix designs were conceptualized, before specialized
stainless steel fiber reinforcement was thrown in
the mix, and even before the project was dubbed MagLev,
the bottom line had to be drawn.
“The [original] track has been here since 1950,
and it’s about a 10-mile-long, dual-rail, rocket
sled test track,” Minto said. Forty-two years
after the first high speed weapons systems testing
began on this Holloman track, Minto and a team of
military personnel and civilians working in the Test
Group determined that testing could be done with a
magnetically levitated rocket sled – and could
accomplish more. Minto just happened to mention the
idea to a visiting congressman, and the next thing
his team knew, they had funding for what is now called
the MagLev Upgrade.
“Suddenly we had $5 million to start developing
the MagLev track and sled system,” Minto said.
“We hadn’t even finished the feasibility
study yet.”
‘Yes,
we can.’
The
faith of a congressman and a military/civilian engineering
team fueled the first leg of MagLev’s journey,
but more than a decade after its birth, the track
is still in its infancy.
“We’re here 13 years later and we’re
still working on it,” Minto said. To date, only
5 percent of the track is complete, but with project
leaders such as San Diego Precast and General Atomics
on the job, confidence in finishing the project has
grown.
Gordon Pettis, project manager for San Diego Precast,
said teamwork was key to MagLev’s success. “I
think you need to have a specific team set up for
this type of customer. Your quality control team has
to maintain and test on a daily basis,” Pettis
said. To ensure the quality control of the precast
concrete rail beams, San Diego Precast followed a
detailed production/curing process and voluntarily
created fail-safe procedures. “You can’t
afford to lose one piece,” Pettis said.
Extruded copper plates, encased in stainless steel,
line the inner channel of the precast units. Due to
the electromagnetic requirements, General Atomics
replaced conventional steel reinforcing bars with
steel fibers in the mix design. This creates a three-dimensional
load resistance system throughout the units, allowing
the MagLev sled, which rests atop the units, to eventually
operate at supersonic speeds close to Mach 10. Standard
steel reinforcement would otherwise interfere with
the electromagnetics, which is the driving force of
MagLev.
Manufacturing these particular units, which measure
13 feet 4 inches long with a 5-foot-wide base and
stand 37 inches tall, involves a lengthy process from
start to finish. The units are set up and poured in
one day. Non-magnetic stainless steel fibers are used
as reinforcement in the top portion of the unit (near
the sled’s superconducting magnets), and carbon
steel fibers are used in the bottom portion. Following
the pour, the units rest in the mold for two days
followed by a five-day water cure.
The units are moved to a preshipment staging area
where they are cleaned and stenciled, and protective
dunnage is attached. Finally, the units are shipped
to New Mexico for installation at Holloman.
This process may seem routine, but the details involved
show that it is anything but routine. For example,
quality control is vital and highly prescriptive.
A seven-day compressive strength test is required
along with a seven-day flexural strength test. Both
compressive and flexural tests are repeated at 28
days. Compressive strengths average 12,500 psi and
flexural strength average is between 2,800 and 3,000
psi, satisfying General Atomics’ strict requirements.
Both are highly ambitious requirements, but the mix
and manufactured units have held up.
“[Our critics] said it wasn’t possible,”
project manager Pettis said. “But fortunately
for us, our company motto is ‘Yes, we can.’”
Testing weapons
systems components
The
Air Force uses MagLev to test vital weapons systems
components in a high-speed environment. Everything
from heat-seeking devices to sensors and warheads
will be mounted atop the MagLev sled and sent speeding
down the test track. A failed heat-seeking sensor
on the nose of a ballistic missile won’t get
the weapon to its target – and for that reason,
among many other scenarios just like it, the MagLev
project is crucial for weapons systems testing. Minto
said a ground-based test facility is ideal for the
type of weapons testing they conduct.
“The United States has fielded missile defense
system sites in Alaska and California to intercept
ICBMs entering the country,” Minto said. “The
best way to test U.S. warhead components is on the
ground. We’re trying to simulate the dynamics
of these missile engagements.”
The
quarter-mile MagLev track being completed this spring
has some limited test capability, but hypersonic weapons
systems testing cannot be accomplished until the track
reaches its desired length of five miles. That completion
date is still unknown as it is based on incremental,
government funding. It is not certain that San Diego
Precast and General Atomics will even complete the
USAF’s project as both of their Air Force contracts
end after the first phase is complete, but both parties
expressed a desire to extend their business agreements.
San Diego Precast and General Atomics may not have
a stake in the project’s future, but talks between
the two have revealed future projects between the
two are a sure bet.
Project Profile
Project Name:
MagLev (Holloman MagLev Upgrade)
Owner:
U.S. Air Force, Holloman Air Force Base, N.M.
Contractor/Engineer: General
Atomics Co., San Diego
Precast Manufacturer:
San Diego Precast Concrete Inc., San Diego*
* San Diego
Precast Concrete Inc. is a certified plant under the
NPCA plant certification program.