Protecting our Power
Post-9/11 concerns brought precast concrete
into the national security spotlight.
By
Daina Manning
America grew more security conscious
in the aftermath of 9/11, as cities from East to West
coasts braced against potential terrorist threats.
The danger to nuclear plants was particularly frightening,
and following 9/11, nuclear facilities needed to move
quickly to increase security.
“The Nuclear Regulatory Commission (called for)
all plants in the United States to upgrade their security,”
says John Bachofer, manager in the purchasing department
for Southern California Edison (SCE) in San Onofre,
Calif. “There was a limited amount of time from
when the order was put out to the time when all nuclear
plants were required to be in compliance.” Even
with an extension, which most plants in the United
States required, shoring up for high-alert status
was a massive undertaking.
At SCE’s San Onofre facility near San Clemente,
Calif., the job was complicated by the plant’s
proximity to the ocean and the regulations of the
California Coastal Commission.
Additionally, the San Clemente community, which already
had concerns about the facility due to seismic faults
beneath the plant, was worried about potential security
problems such as a plant employees’ parking
lot, which could be accessed by visitors to nearby
San Onofre State Beach.
SCE took action
In addition to such precautions as extensive background
checks for employees, intruder-alert systems, metal
and explosives detectors, and increased Coast Guard
patrols of the five-mile exclusion zone outside the
San Onofre plant, the plant needed additional barriers
to counteract the possibility of truck bomb, a known
terrorist device.
An immense project to construct effective barriers
that doubled as attractive planters was conceived
and implemented at breakneck speed, thanks to the
versatility, adaptability and strength of precast
concrete, the exclusive choice for the job.
The biggest challenge was the time frame, notes Warren
Taylor, president of Pro-Cast Products Inc., Highland,
Calif.
“The job bid in two weeks, and we had eight
to 12 weeks to complete the whole (project). That
included forming, casting and delivering,” he
says. “We literally had to have forms up and
running in three weeks from the time the job bid,
and the form work was quite extensive.”
Because of the short timeline, Bachofer says that
the facility outsourced the job instead of relying
on its own engineering and facilities staff. Pro-Cast
Products won the competitive bid due to the company’s
expertise in handling substantial construction projects
that included highway barriers, tanks and retaining
walls.
“Of course we’re concerned with price
because it’s the rate-payers’ money we’re
spending,” Bachofer says. “But we also
had to ensure we were dealing with someone who had
the capacity to build the quantity we were asking
for – and who was relatively local so we didn’t
incur great shipping costs.”
The job included 150 massive planters designed to
prevent vehicular intrusion by absorbing the impact
of a large vehicle. Taylor says the project demanded
precast concrete from the start because of the logistics
involved. The cast-in-place process for such bulky
and sturdy forms would have been much more complex
than precasting in an already-operating facility.
As for the decorative part of the process, the planters
feature an integral color, which coordinates nicely
with the recreational areas surrounding the facility.
“The California Coastal Commission has requirements
that in the coastal zone, which we’re in, non-obtrusive
colors blend in with the naturally occurring background
in the area,” says Ray Golden, communications
manager for SCE in San Onofre. The chosen color, San
Diego Buff, “is very close to the color of the
indigenous sand, the San Mateo sand.”
Transporting the finished pieces to San Onofre was
another difficult part of the project, Taylor recalls.
The planters weighed about 55,000 pounds each, so
Pro-Cast Products had to truck them one at a time
80 miles from its facility to the nuclear plant.
“It took a little bit of work,” Taylor
says. “We would do three to four pieces a day.”
Still, the procurement process came off “without
a hitch,” Bachofer says. “The people we
chose were wonderful, and delivery was not a problem.
I think the hardest part for us was the fact that
we were closing off one of our gates that goes into
the power plant.”
Bachofer explains that the lines of planters from
both ends joined in the middle at the gate, which
was to be closed off, so at one spot they had to fabricate
a piece of one planter in place to make it all join
up. “But we have good masonry people here, so
we were able to pull that off,” he says. He
can’t talk about the actual construction of
them for security reasons, “but precast was
selected because of the way it can be made very strong
with the mix of the concrete, which we specified.”
Presently, purple and orange flowers grace the planters,
and are tended by an in-house facilities management
staff. “They handle all the infrastructure of
the property,” Bachofer says.
And the community reaction?
“I don’t think they can see (the barrier),
although we’re in close proximity to a popular
surfing beach to the north and a state campground
to the south,” Golden says. “The way the
walls are configured, it’s in a large parking
lot that’s private property. But in general,
we’ve always tried to be as unobtrusive as we
can, to blend in with the natural environment.”
And with its chameleon-like ability to change form
and texture, precast concrete was the most logical
choice.
Project Profile
Project Name:
San Onofre Nuclear Generating Station – Parking
Lot No. 4
Owner/Conctractor/Engineer:
Southern California
Edison, San Onofre, Calif.
Precast Manufacturer:
Procast Products Inc., Highland, Calif. *
* Procast Products
is a certified plant under NPCA’s Quality Assurance/Plant
Certification program.