Taking advantage
Precast concrete proves itself at a
new sewer district in Indiana.
By
Bridget McCrea
Building an entirely new wastewater
treatment facility from scratch is a monumental task
that involves a combination of coordination, patience
and persistence to achieve. The city of Rockfield,
Ind., recently built a 30,000-gallon-per-day plant
to handle the growing municipality’s wastewater
treatment needs. The municipality decided to make
the switch from individual septic systems to a citywide
wastewater treatment system, supported by the new
facility.
Precast concrete was the material of choice for the
treatment tanks – a decision that not only eased
the burden of installation and backfilling, but saved
the municipality time and money. Designed by GRW Engineers
of Indianapolis, the wastewater facility includes
five 18,000-gallon precast septic and dosing tanks
that can handle 30,000 gallons of daily capacity.
Jim Shields, PE, project construction engineer at
GRW, said the facility was built around a recirculating
media filter used to “dose” or treat the
wastewater four times before discharging it. The precast
dosing tanks collect the clean, filtered water in
a four-to-one ratio: three parts clean water, and
one part “gray” water from the septic
tank.
“From there, you’re basically just recirculating
that water over the top of the media filter,”
said Shields. “The dosing tank basically serves
as a volumetric storage basin.”
Shields said his firm was selected by the Rockfield
Regional Sewer District to assess the municipality’s
needs and utilize a preliminary report prepared by
another engineer. “We came in and evaluated
that engineer’s report and their options,”
Shields said. “Then we came up with the collection
and treatment system that was subsequently built.”
Careful Selection
Before choosing precast concrete, Shields said the
engineers considered fiberglass tanks, but ruled out
the material based on cost. “The whole idea
was to have the system built off site and installed
in components,” he said. “We were trying
to avoid a lot of specialty contractors and/or construction
employees on site. Instead, we wanted it built off
site, brought to the job and installed.”
Mark Wieser, vice president of Wieser Concrete Products
Inc., Maiden Rock, Wis., said that early in the bidding
phase, the municipality didn’t realize that
precast concrete tanks large enough for the project
were even available. “We showed them what their
options were in terms of the standard tanks,”
Wieser said. “We showed them how much more cost
effective it would be to use precast.”
Taking the time to educate the potential customer
about the merits and capabilities of precast concrete
paid off for Wieser, who ultimately won the bid to
produce the tanks. Shields said precast won out on
cost and was used to manufacture the five 18,000-gallon
tanks. And while the material cost for fiberglass
versus precast concrete was comparable, he said installing
fiberglass tanks was cost prohibitive. That’s
because fiberglass tanks would require granular bedding
backfill around the tanks, which would necessitate
the hauling of such materials to the job site.
“With precast, we were able to use the native
soil that was excavated and backfilled around the
tanks,” said Shields, “making it a less
expensive option.” Comparing fiberglass to precast
concrete, he estimates that installation and construction
cost about 90 cents per gallon, compared to $1.30
per gallon for fiberglass. The choice of precast concrete
also helped move the project along faster –
complete installation took just two days, allowing
them to progress to the next phase of the project.
Wieser noted that all tanks were vacuum tested and
required post-inflation testing according to ASTM
C1227 “Standard Specification for Precast Concrete
Septic Tanks.” There were few other design challenges
and no special load considerations for the precast
concrete side of the project, which was completed
in June 2004.
Measured
Advantages
Terry Piatt, project manager of RE Crosby Inc., Fort
Wayne, Ind., helped with the installation. He said
the firm has worked on similar projects in the past,
many of which utilized cast-in-place concrete. He
said it didn’t take long to see the benefits
of using precast concrete on this particular project.
“The advantage for us is that weather doesn’t
play as much of a factor as it does with poured-in-place,”
said Piatt. “You can basically get your hole
open, bring the material in and have it all set in
a day. Then we started the backfill right away, rather
than keeping a hole open for a month or more while
pouring the concrete.”
Piatt said the time saved translated into labor saved
that wouldn’t have otherwise been achieved.
Installation went smoothly and quickly, with the contractor
having only to open the holes in the ground, put in
the precast structures and start hooking up pipes
and installing filters.
“Overall, precast made our job a lot easier,”
Piatt said, adding that the project owners are anxiously
waiting waiting for another contractor to complete
a collection system so they can begin using the new
plant. “When we had our walk-through recently,”
he said, “they appeared to be very pleased.”
Shields agreed and said the treatment plant is nearly
finished. Homes in the community are currently being
hooked into the collection system, which was bid as
a separate contract from the treatment plant itself.
“Everything is going very well with the precast
portion of the project playing a role in that success.”
Project Profile:
Project Name: Septic and
dosing tanks for a 30,000-gallon per day wastewater
treatment plant
Owner: Rockfield Regional
Sewer District, Rockfield, Ind.
Engineer: GRW Engineers,
Indianapolis, Ind.
Contractor: RE Crosby
Inc., Fort Wayne, Ind.
Precast Manufacturer: Wieser
Concrete Products Inc., Maiden Rock, Wis.*
* Wieser Concrete
Products is a certified plant under NPCA’s Quality
Assurance/Plant Certification program.