Perfect Interception
Precast is the material of choice for
grease interceptor, septic tanks and pump tank at
outdoor wilderness camp.
By Bridget McCrea
It’s
not often that children and families who live in the
city get to experience the excitement of a rural,
outdoor camping adventure. Thanks to the long-time
director of Phoenix’s Parks and Recreation Department,
they’re getting to do just that and more at
Camp Colley.
This 3-year-old wilderness camp
in northern Arizona fulfills a long-time dream of
camp creator James Colley, who recently passed away:
to give vulnerable youngsters a new, hopeful view
of the world through outdoor adventure.
Located about 50 miles north of
Payson, near the Blue Ridge Reservoir at an elevation
of 6,700 feet, the camp provides structured, supervised
recreational opportunities for children and families.
The camp recently underwent expansion and now features
a dining hall supported by several precast concrete
wastewater collection structures that were manufactured
and installed in fall 2005. When this second expansion
phase is complete, there will be a bath house and
cabins that can accommodate groups of up to 60 people.
Joan Gable, engineer with Phoenix-based
Wass, Gerke and Associates specializing in wetlands
treatment, says the first phase of the camp expansion
included the design and construction of a dining hall
(by Amon Builders of Payson, Ariz.), the drinking
water system upgrade, and the wastewater treatment
system that is comprised of several underground precast
structures, as well as a treatment wetland feature.
Gable says her firm has been involved with Phoenix’s
wetlands research and design for several years, including
a proposed 300-acre wetland facility in the city.
“The Parks and Recreation
Department wanted to incorporate constructed wetlands
into the on-site treatment system as an educational
opportunity provided at Camp Colley,” Gable
says. “We were brought in to design the on-site
wastewater treatment system primarily to include the
subsurface wetland as part of that opportunity.”
The completed on-site wastewater treatment system
is comprised of the grease interceptor, a septic tank,
a sub-surface constructed treatment wetland, a dosing
tank and drip irrigation field.
A typical subsurface treatment wetland
is a constructed basin with a 2-foot depth of gravel
media where the wastewater flows through the porous
gravel matrix. Wetland plants, such as bulrush and
cattail, are planted in the gravel matrix. The wastewater
travels through the plant root zone and is treated
by the microbial community living in that zone. The
plants take up water and nutrients as well. The result
is a highly treated wastewater discharging out to
a drip irrigation field.
Wass, Gerke and Associates also
designed the additional collection and treatment aspects
of the system, for which it considered several materials
and options before selecting precast concrete. Fiberglass
was one option, Gable says, based on the issues surrounding
the existing bedrock and excavating costs.
“Product and delivery costs
(for delivering the product up into the mountains)
were also issues,” Gable says, “which
is why we steered away from fiberglass.” Gable
says she found a better solution when the project’s
excavator, Smith & Sons Excavating of Flagstaff,
Ariz., pointed her in the direction of Prescott, Ariz.-based
Yavapai Precast.
Gable
spoke with the precast firm’s sales manager,
Mark Boehle, and discovered that precast concrete
would be ideal for the project. The firm designed
a system that collected the treated water, which in
turn dosed out into a drip irrigation field. A grease
interceptor, situated before the septic tank, protects
the other system components – precast septic
tank, wetlands and drip field – from clogging.
For the Camp Colley project, the
precaster manufactured and delivered a 1,700-gallon,
two-compartment grease interceptor, 5,500-gallon and
2,500-gallon septic tanks, and a 2,500-gallon pump
tank. All interconnected, the pieces serve as both
the grease interceptor for the dining hall and the
wastewater treatment system for the camp.
Working quickly
A winter season known for making an early appearance
in Arizona’s higher elevations threatened contractors
on the Camp Colley project. With ground-freezing temperatures
in mind, the project’s owners fast-tracked a
tight timeline for getting the underground work completed.
“We specified it knowing that Yavapai Precast
was close by, and that they could fabricate it, deliver
it and have it put in place within five weeks,”
Gable says.
Boehle says the tight schedule presented
challenges for the precaster, but not enough to hold
the project back in any way. Already in the throes
of its busy season, the firm kicked into overdrive
to help the city button up the project before winter
hit.
The
product design itself was straightforward and basic,
Boehle says, who estimates that the city saved approximately
30 percent to 40 percent in manufacturing costs by
using precast concrete over fiberglass. Lead times
for the latter were much longer, he adds, making precast
all the more attractive for the time-strapped project.
“We were able to set everything up and have
it done within five weeks,” Boehle says. “That
was a very big consideration for the project’s
owners.”
From the engineering perspective,
Gable says her firm’s challenges included developing
a system that could fit in a tight space. Setback
constraints for the camp itself and the surrounding
ephemeral washes gave the firm little wiggle room.
“We were also piping in several different buildings,
where previously just one septic line ran from a cabin
to the system,” Gable says, who adds that Yavapai
Precast also provided the required manhole. “It
was great to be able to go through one vendor who
not only made everything, but delivered it too.”
With the deliveries complete, Smith
& Sons took over. Richard Smith, Smith & Sons
president, says the company worked from mid-August
to mid-September hammering out “extensive amounts
of rock” to achieve the desired result.
Smith credits Yavapai Precast with
manufacturing a quality system that was easy to install.
Dining out
Gable says precast not only saved money on the Camp
Colley project, but also provided a sound foundation
for the creation of the desired wetlands. The treatment
wetlands are a natural system requiring minimal maintenance
as long as the mechanical and hydraulic structures
operate properly.
The precast tanks before and after
the wetlands can provide the owners and caretakers
reassurance that the treatment wetlands can perform
optimally. With winter looming, she says the speed
at which the grease interceptor and ancillary products
were developed, manufactured and installed also went
a long way toward creating a successful project. When
the thaw comes to Camp Colley next spring, the wetland
vegetation will be planted and given time to grow
and stabilize in time for the camp summer season.
Once the Camp Colley caretaker is
trained on the maintenance and usage of the grease
interceptor, Gable says the system, which was meant
to accommodate future camp growth, will be ready for
use.
“It’s a very low-maintenance
system that’s designed for commercial use,”
Gable says. “As with any design, we wanted to
make sure we were providing the camp with a safe,
beneficial system as a way to ward off any future
issues.”
Project:
Camp Colley grease interceptor, septic tanks and pump
tank for dining hall at outdoor w ilderness adventure
camp
Owner: City of Phoenix
Engineers: Wass, Gerke
& Associates, Phoenix
Contractor/Installer:
Smith & Sons Excavating, Flagstaff, Ariz.
Precast Manufacturer:
Yavapai Precast, Prescott, Ariz.