 |
Precast
Solutions |
 |
|
Precast
Goes Collegiate
Precast Serves As The Material Of
Choice For A New Community College Residence Hall In New York.
By Bridget McCrea
Monroe Community College in Rochester, N.Y.,
ranks as one of the top 11 community colleges in the nation
and serves as a model for 1,200 other schools of its size,
according to The New York Times. Since 1980, MCC students
have advanced to more than 400 colleges and universities –
including Ivy League schools, state universities, international
institutions and historically black colleges. This level of
success naturally attracts more students. But the flipside
of MCC’s popularity is that it ran out of room for hundreds
of students seeking housing. To address the housing demand,
last year the MCC Board of Trustees approved construction
of a new residence hall for its Brighton campus, adding a
second phase to a plan to expand student living quarters.
Precast concrete figures prominently in both phases of the
housing project, according to David Hofmeister, P.E., project
executive for Rochester-based DiMarco Constructors, the general
construction firm that handled both phases.
“They were happy with phase one and
selected us to handle the most recent project,” Hofmeister
says. Phase two calls for precast load-bearing walls, stair
shafts and stairs with acid-etched insulated panels on top.
A thermal mass composite system was used to build the insulated
panels, and the floors are hollow core. In total, about 274
precast walls, 21 shaft units (which created six stair shafts
and two elevator shafts) and 110,000 square feet of 10-inch
hollow core floors are being installed.
The Fine Points
Community leaders in Rochester established Monroe Community
College in the early 1960s to fill a need for nursing education
in the region. Led by local physician Dr. Samuel J. Stabins,
MCC’s mission was to prepare students for work in local
hospitals and health care facilities. MCC became part of the
State University of New York system, and its program offerings
were expanded to prepare graduates for a wide range of job
fields or transfer to four-year institutions.
MCC’s
first class of 720 students enrolled in September 1962. Since
then, enrollment has increased steadily and new programs have
been developed to meet the changing requirements of the local
community. With more students enrolling, the college found
itself and its students without enough on-campus housing.
Phase one of the project houses approximately
10 percent of the school’s student body, while phase
two will accommodate an additional 8 percent. Built in a seven-pod
configuration, the new dormitory comfortably fits more than
360 new beds, with each pod comprising four separate apartments,
each of which contains two or three bedrooms, living space,
a kitchenette and two bathrooms.
To handle the job, DiMarco selected three
precast concrete manufacturers: Empire Precast of Rochester;
Lakeland Concrete Products of Lima, N.Y.; and Jefferson Concrete
Corp. of Watertown, N.Y. Jim Boyce, president of Empire, says
his company was involved in phase one and was called upon
by DiMarco to consult on the second half of the project. “We
pulled together the team that did the actual precast design,”
says Boyce. “Then we helped DiMarco bid out the different
parts of the project.”
Boyce says the expediency of installation
and the durability of the product were the two key reasons
MCC selected precast concrete. Casting started in July 2006,
and the precasters moved on site in October and spent the
next six to eight weeks installing the pieces.
Todd Clarke, president of Lakeland Concrete
Products, says the fast erection time and the fact that the
materials required no exterior or interior finish work beyond
painting, made precast concrete especially attractive for
the residence hall project.
“Within
the building itself there is drywall and some finishes, but
the dorm rooms themselves are all precast,” says Clarke,
whose firm manufactured 156 insulated and 118 noninsulated
precast walls that varied in size from 8 feet by 10 feet to
10 feet, 2 inches by 35 feet, 3.5 inches. The panels were
shipped to the site and staged in trailers, which were then
moved around to the specific construction zones as needed.
“Every piece was laid out in the trailer for the erector
to pick and use,” says Clarke. “They had everything
they wanted right when they needed it.”
Precast Advantage
When working with the various contractors and engineers to
lay out the MCC residence hall project, Doug Morlock, associate/project
manager at Kideney Architects in Buffalo, N.Y., says precast
concrete stood out as the best possible choice for several
reasons, not the least of which is its fire-resistance ratings.
Noise reduction was another key criterion, says Morlock, because
the precast significantly reduces floor-to-floor transfer
of noises.
“You’re
using concrete plank instead of a more hollow (or less dense)
material that could cause sound transfer from one apartment
to another,” says Morlock, who points out that concrete’s
thermal characteristics also create more energy-efficient
structures – something not all of today’s college
dormitories can boast. “One of the big selling points
for the project – and for phase one – was the
fact that this building was to be constructed of concrete,
as opposed to being predominantly wood frame like most dorms
are.”
But while the 100 percent concrete approach
worked well for the project’s owners and contractors,
it posed some special challenges for the precast concrete
manufacturers themselves. For example, Clarke says each piece
was extremely detailed when it came to matching up connections
between cast-in-place footers and the precast panels, and
between the precast pieces themselves.
“There were mechanical connections
in there that had to be carefully matched up,” says
Clarke. To handle the challenge, the company relied on its
quality control processes during the actual manufacturing
to ensure that the mechanical connections were in the right
spot – and useable once installed. “They checked
everything very carefully, because if the sleeves were in
the wrong locations, we wouldn’t have been able to connect
the panels,” says Clarke.

Conduit and electrical boxes were also inlaid
in the panels. “There was no surface mounting of electrical
boxes or anything required within the rooms themselves,”
says Clarke. “It’s all integrated into the panels
themselves.”
Jumping Hurdles
The MCC site itself also presented hurdles for the team working
on the new MCC residence hall, according to Hofmeister, who
says existing site materials had to be moved, trees removed
and new gravel and soil installed under the structure to serve
as the building pad. The permitting process through the town
of Brighton also took some time, which set construction back
a few weeks.
Working on an aggressive timeline, Hofmeister
says getting those early aspects of the project completed
quickly was of utmost importance. “We needed to get
the site work accomplished and foundations in before winter
so that we could set all of the precast,” says Hofmeister.
“It was pretty tricky.”
The precast helped to pick up some of the
slack, since the pieces were constructed off site at the various
manufacturers’ facilities. “The speed with which
we were able to erect the building, roughly eight weeks, was
certainly a benefit,” says Hofmeister. “It allowed
us to close in the building pretty rapidly to allow interior
finish work to begin, which was critical given the severe
weather elements here in the Northeast during the winter.”
On track for completion in July, the project
is going smoothly, according to Hofmeister, and will be ready
to welcome a new group of 360 residents in the fall. “The
project owners are happy,” says Hofmeister. “It’s
been a pretty good experience for them, with very few problems.
The ride has been relatively smooth.”
Project Profile
Project: New seven-pod dormitory
at Monroe Community College’s Brighton Campus in Rochester,
N.Y.
Project Owner: Monroe Community
College Association Inc.
Design/Builder: The DiMarco
Group, Rochester, N.Y.
General Contractor: DiMarco
Constructors, Rochester, N.Y.
Architects/Engineers: Kideney
Architects, Buffalo, N.Y., and Q-Tech Engineering, Rochester,
N.Y.
Precast Companies: Empire
Precast, Rochester, N.Y., Lakeland Concrete Products, Lima,
N.Y., and
Jefferson Concrete Corp.*, Watertown, N.Y.
*Jefferson Concrete Corp. is an NPCA
Certified Plant
Back
to Precast Solutions Summer 2007 Table of Contents
Bridget McCrea
is a freelance writer who has covered manufacturing, industry
and technology for more than 11 years.
|